‘Blue Wave’ Midterms to Postpone Some Data Centers

Data Centers, Energy Transfer, Kinder Morgan, Natural Gas, The Daley Note, Williams

Posted by:

Newly elected Democratic governors in Texas, Georgia and Ohio will likely delay some data center projects and related gas demand, though not outright cancel them. Texas carries nearly all the near-term hit, and the nationwide push for data centers to generate their own power could leave each new campus potentially burning more gas, not less, over the long term.

In East Daley’s base case, government actions push roughly 10% of the current 2028 data center gas demand we forecast into later years. The gap narrows to ~2% by 2030, because most delayed projects will still be built in Texas or elsewhere. Our base case is available in the ‘Data Centers’ dashboard in Energy Data Studio (see figure below of the Texas outlook).

The Texas Pause Already Bites

New data centers were already on hold in Texas before the elections. On Sept. 21, Texas Gov. Greg Abbott issued a directive halting state approvals for key permits needed for projects, including air and water permits, until ERCOT and the Public Utility Commission of Texas (PUCT) finish a review of planned data centers. The audit is due Dec. 10.

Governor-elect Gina Hinojosa, who takes office Jan. 19, has promised voters an executive-order moratorium on new data centers until the Texas state legislature addresses the issue, outside of the ERCOT audit. The state Senate remains in Republican control, so there is uncertainty around what the outcome of that potential action would be.

Hinojosa’s victory will likely put more distance between first-mover projects and those planned later in the cycle. Permits issued prior to the Sept. 21 moratorium remain in effect, and around 40% of Texas data center gas demand in East Daley’s forecast comes from campuses with power plants that were permitted before the pause. These include Pacifico’s GW Ranch, permitted in January 2026 for 7.65 GW of on-site gas generation.

Energy Transfer (ET) has the most direct exposure to data centers through its announced supply deals for the Fermi and CloudBurst projects. Fermi’s first phase is permitted, but its second was pending as of the moratorium, and CloudBurst has not attained a live generation permit.

Kinder Morgan’s (KMI) Permian Link expansion also has possible risk. KMI in late October took a final investment decision (FID) on the Permian Link expansion of Natural Gas Pipeline of America (NGPL), targeting 2030 service. KMI said Permian Link is backed by a large hyper-scaler developer based in the Texas Panhandle, inside the pause zone. We don’t know whether the anchor shipper bears risk from further permitting delays.

Georgia Risk Runs Through Georgia Power to Infrastructure

Georgia governor-elect Keisha Lance Bottoms also promised voters a statewide pause on data center development, but hasn’t released a formal plan. Democrats also flipped Georgia’s Public Service Commission (PSC) to a 3-2 majority.

While the PSC regulates Georgia Power and not pipelines, the risk to infrastructure is that the agency clips Georgia Power’s ability to permit new gas plants, which are the main demand source behind expansions on KMI’s Southern Natural Gas (Sonat) and Williams’ (WMB) Transcontinental systems. KMI also just announced FID on Sonat’s Southeast Connector, a project we expects is backed heavily by Southeast utilities.

Pause Length Sets the Risk

We haven’t adjusted our outlook for data centers already under construction. Projects without permits bear most of the risk for longer delays. The industry may shift new announcements toward states without data-center pauses.

  • Upside: If the Texas pause ends by mid-2027, we expect minimal impact to our current 2028 demand forecast.
  • Downside: If the permitting pause runs into 2029, we’d expect a more significant hit to demand to emerge in the 2028-30 period. Our initial forecast is for ~15% of 2028 demand to slip, and the losses widen by 2030. The downside grows if more states block on-site plants too, as Texas and New York do today.

Bring-Your-Own-Power Favors Gas

Many states now want data centers to build their own power. Ohio Gov.-elect Amy Acton’s conditional moratorium requires it, and Pennsylvania’s GRID standards push the same way. On-site plants mostly run on gas, while a grid-served campus burns gas only for the share of grid power that gas supplies. Fewer data centers can still mean more gas per data center.

Investor Takeaway: We expect 2026 midterms will defer some data-center gas demand, though many later-stage projects will continue with business as usual. ET carries the most direct timing risk from the Texas handover, and KMI and WMB carry Georgia Power forecast risk. Watch ERCOT’s Dec. 10 audit and Hinojosa’s first orders after Jan. 19. – Jaxson Fryer Tickers: ET, KMI, WMB.

 

Data Center Headwinds – Could They Ripple Through Energy Infrastructure? 

Data centers are driving expectations for major new power generation projects — but what if projects are delayed? The effects could reach far beyond the data center sector.

Join East Daley on Wednesday, Nov. 18 at 10 am MT for a look at how data center headwinds and power generation needs could reshape energy infrastructure and production.

We’ll explore:

  • Power demand and project timing: What could delay data center buildouts, and would that affect expected demand for new generation?
  • Natural gas infrastructure: Could delays put natural gas projects at risk where data centers and power utilities are the main downstream customers — especially projects already at FID or still in wait?
  • Cross-commodity spillovers: If gas demand growth is pushed out, what does that mean for midstream crude and NGL project growth — and for overall hydrocarbon production?

Delays in data center and power project development could ripple through the infrastructure pipeline, changing the timing and scale of investment across multiple commodity markets.

Reserve your spot now to join the discussion. 

 

Introducing The LNG Reckoning, East Daley’s Latest White Paper

East Daley Analytics has published our latest white paper, The LNG Reckoning. Surging LNG exports are colliding with new data center demand, setting the stage for disruptions in the US natural gas market. We view midstream, not resources, as the primary bottleneck, and expect problems to emerge based on the interdependency of energy commodity chains. In The LNG Reckoning, we identify the potential choke points ahead. Download a copy now.

 

The Daley Note

Subscribe to The Daley Note for energy insights delivered daily to your inbox. The Daley Note covers news, commodity prices, security prices and EDA research likely to affect markets in the short term.

SUBSCRIBE TO THE DALEY NOTE

Recent Posts