South Bow (SOBO) on May 29 announced open season results for its Prairie Connector project, securing 20-year binding commitments from Hardisty, Alberta to US delivery points. The company also revealed several key project details, giving the market more visibility on a potential new Canadian crude egress path.

The project would add 380 km (~236 miles) of new 36-inch pipe and use 150 km (~93 miles) of preserved 36-inch pipe, plus two existing pump stations. Based on a typical oil pipeline flow velocity of 3-10 ft/sec, a 36-inch line implies ~300-1,100 Mb/d of theoretical capacity. SOBO is targeting a final investment decision (FID) by mid-2027.

Prairie Connector would run to the US-Canada border and connect to a companion project planned by True Companies’ Bridger Pipeline (see map at right from SOBO). Bridger has filed with Montana regulators to build a 36-inch crude oil pipeline from Phillips County, MT to the Guernsey hub in Wyoming.

The commercial readthrough is constructive, but Prairie Connector still carries more execution risk than a competing plan by Enbridge (ENB) and Energy Transfer (ET) to move Canadian crude through the Bakken. The companies are pursuing a more brownfield strategy: ENB would reverse flow on the Bakken Pipeline and tie it into the Dakota Access Pipeline (DAPL), using spare capacity on DAPL to move Canadian barrels to the Midwest. That approach should reduce regulatory risk vs a greenfield cross-border build, a key distinction after the Keystone XL, Northern Gateway and Energy East projects all failed following years of regulatory, political and stakeholder pressure.

Politics may be the swing factor. South Bow still needs permits, stakeholder engagement and financing before reaching FID. A supportive US and Canadian policy backdrop could help convert binding commitments into a sanctioned project. However, a political shift in either country could raise the cost of capital, extend permitting timelines or strand the project before a final decision.

Prairie Connector also doesn’t resolve the full egress problem. Bridger’s companion project would move ~550 Mb/d from the US-Canada border to Guernsey, WY, where East Daley’s Crude Hub Model shows only ~100 Mb/d of spare takeaway today. We expect Tallgrass Energy will pursue an expansion of its Pony Express system if the Bridger/Prairie Connector projects move forward. Pony already runs above its 300 Mb/d nameplate capacity out of Guernsey, averaging ~312 Mb/d in 3Q25. A Pony loop would create the commercial backbone to move heavy Canadian crude to Gulf Coast refiners.

Investor Takeaway: Watch political swings in the US and Canada as closely as SOBO’s 2Q26 disclosures, Bridger’s permitting schedule, and any Tallgrass/True commitments on Pony Express. Prairie Connector’s open season de-risks the Canadian leg, but politics could make or break South Bow’s ability to turn commitments into steel in the ground. – Garrett Streit Tickers: ENB, ET, SOBO.

 

 

Download Part II of East Daley’s Permian Basin White Paper Series

The Permian Basin’s next big buildout is already taking shape, but this time the driver isn’t crude oil. In The Permian Basin at a Crossroads: Why This Pipeline Boom is Different, East Daley Analytics’ latest white paper reveals how gas demand from AI data centers, utilities and LNG exports is rewriting the midstream playbook in the leading US basin. Over 10 Bcf/d of new capacity and $12 billion in investments are reshaping flows, turning the Permian into a gas powerhouse even as rigs decline. Read Part II: Why This Pipeline Boom is Different

 

The Daley Note

Subscribe to The Daley Note for energy insights delivered daily to your inbox. The Daley Note covers news, commodity prices, security prices and EDA research likely to affect markets in the short term.

SUBSCRIBE TO THE DALEY NOTE

Recent Posts