Plaquemines LNG Takes First Gas in Project Milestone

Written by East Daley Analytics | Apr 30, 2024 12:00:00 PM

Venture Global’s Plaquemines LNG has started receiving natural gas, marking a milestone for the project under construction in southeastern Louisiana and a reminder of new demand ahead in 2024.

Gator Express is comprised of two co-located pipeline laterals, both with a capacity of ~1.9 Bcf/d. Venture Global placed Phase 2 of the project in service; Phase 1, which interconnects with the Texas Eastern Transmission (TETCO) and Tennessee Gas pipelines, has encountered unexpected delays.

The start of gas flows comes nearly three weeks after TETCO received the go-ahead from the Federal Energy Regulatory Commission (FERC) to start service on its own project, the Venice Lateral extension, connecting to Gator Express.

The 36-inch Venice Lateral runs three miles from TETCO’s Line 40 and replaces an existing 2.2-mile segment. Owned by Enbridge (ENB), TETCO also constructed a new compressor station in Pointe Coupe Parish, LA to replace two existing compressors in Iberville and Lafourche parishes. With the compression, the new line will have a maximum capacity of 1.26 Bcf/d from TETCO’s Louisiana mainline to feed Gator Express.

Plaquemines is part of the next LNG project wave set to transform the US natural gas market through 2030. East Daley Analytics tracks Plaquemines and other Louisiana-based LNG projects in the new Southeast Gulf Supply and Demand Forecast. The Southeast Gulf forecast combines our regional supply forecasts for the Haynesville and other Gulf Coast basins with midstream pipe flows/expansions and new LNG demand, for a comprehensive view of the regional gas market. The figure shows EDA’s forecast for pipe flows in the southeastern Louisiana sub-region of the Southeast Gulf Forecast.

The progress at Plaquemines will come as welcome news for Haynesville producers contending with oversupply and prices under $2/MMBtu this spring. Market conditions have been so poor that producers in Louisiana and East Texas have been underdelivering on pipeline nominations, causing Haynesville samples to decline rapidly.

The Plaquemines LNG project appears to be progressing ahead of schedule. At CERAWeek in March, Venture Global announced that Plaquemines would begin taking gas sometime in June, with first LNG production expected this summer. East Daley forecasts Phase 1 of Plaquemines LNG (2.25 Bcf/d) to ramp to full capacity by 2Q25. – Oren Pilant Tickers: ENB.

 

Gain a Competitive Edge with Southeast Gulf S&D Report

Gain an edge in natural gas with the Southeast Gulf Supply and Demand Forecast. East Daley’s latest product connects supply, demand and midstream developments in the most dynamic regional market. The Southeast Gulf S&D Forecast tracks and forecasts Haynesville production in East Texas and Louisiana, regional pipeline and midstream expansions, and Gulf Coast LNG projects for a comprehensive view of the Louisiana - Gulf Coast market. Learn more about the Southeast Gulf Supply and Demand Forecast.

 

Join EDA’s Natural Gas Webinar on May 8 - “The Case for More Volatility”

EDA will host an upcoming natural gas webinar on May 8. In “Finding Equilibrium: Seesaw Natural Gas Markets and the Case for More Volatility”, we review the big factors impacting natural gas markets: Production has retreated across most basins, but for how long? What will be the impact of summer gas-fired power burn and looming LNG demand? Will infrastructure challenges create new hurdles? We’ll also look at storage inventory and the price outlook. Sign up to join our webinar on May 8.

 

Access the NEW G&P System Financial Dashboard

We are thrilled to introduce a groundbreaking addition to East Daley's suite of energy management tools: the G&P System Financial dashboard. This dynamic tool is designed to revolutionize how you scope and analyze multiple financial metrics and throughput forecasts for individual G&P systems across the US. Clients can log in to Energy Data Studio to review the G&P System Financial dashboard protype. Learn more here.

 

Energy Data Studio

East Daley Analytics has launched Energy Data Studio, a platform for our industry-leading midstream data and commodity production forecasts. All clients have access to the new client portal. If you have not yet logged in, please fill out the form to request a registration email be resent.

Energy Data Studio leverages our G&P data set for insights into midstream assets across every major oil and gas basin in North America. Users can navigate detailed visual dashboards by region, pipeline, or individual asset to understand crude oil, natural gas and NGL supply at the most granular level.

Energy Data Studio is available through data downloads from the visual interface, in Excel files, or as a direct feed delivered into subscribers’ workflow via secure file transfer. To learn more about Energy Data Studio, please contact insight@eastdaley.com.

 

The Daley Note

Subscribe to The Daley Note (TDN) for midstream insights delivered daily to your inbox. The Daley Note covers news, commodity prices, security prices and EDA research likely to affect markets in the short term.